MONITORING REPORT
Technological and Environmental Management Network Ltd
DREDGING AND RECLAMATION PROGRAMME IN
The R1 bund preparation
continues:.
Monitoring trips
were carried out on the following dates:
Thursday 27th
December: Aerial flight bserving the dredging operations connected with the
preparation of the R1 Bund. (Photo attached)
January 3rd Bund preparation inspection
No screens visible.
WATER QUALITY SUMMARY (DATA AND OBSERVATIONS)
1)
Background data collected by TEMN for
the EIA indicated low background levels of suspended solids in
2)
Data collected by Jan De Nul on November 29, (just
before the start of the
dredging) indicate
much higher background levels of suspended solids in
100 -150mg/lat the surface
400 – 600mg/l 1.5m below the surface
Off scale (>1000mg/l ?) 20 – 30cm above the floor of the sea
3) Data collected by Jan De Nul
on December 13, during the dredging indicated:
Suspended
solids concentration of 50 – 150 in the upper 1m of the water column;
Suspended solids concentration of 700 - > 1000 near the
sea floor.
For
Suspended
solids 10 – 30mg/l in the top 2.5m of the water column
Suspended solids 100 – 400 mg/l .5m above the sea floor.
For the dredge site (channel)
Suspended solids of 100 – 250mg/l in the upper .5m of the water
column.
Suspended solids relatively
uniform at depths greater than .5m. below the surface.
East
of The Dredge (just outside the channel)
Suspended solids 0 – 10mg/l from .5m below the surface to 1m from the sea floor.
4) Visual observations made during the operation of the dredge indicated a plume that settled readily. Young fishers could be seen operating from a beacon near the dredge.
·
Background data collected by JDN for
suspended solids are much higher than that collected by TEMN (factor of ten).
This could indicate the highly variable conditions that can exist in the Bay.
·
Suspended solids taken by JDN in hunts
Bay during the dredging (Dec 12), indicate turbid conditions in the Bay similar
to JDN November 29 data
·
In Hunts Bay the station near the
causeway bridge had a suspended solids level less than JDN background levels.
This could indicate the stability of the bund.
·
At the dredge site the impact of the
dredging was evident and uniform throughout the water column.
·
The low Suspended solids value
determined for the site to the east of the dredge indicated little risk to the
Port Royal Mangroves at the time.
·
The rapid disappearance of the plume could indicate the rapid
settling of coarse material being dredged at the time.
Table
1
Indicator Parameter |
Phase 1 Background Levels |
Standard/Criteria value |
Total suspended solids (TSS) mg/l |
0 -7 |
<10mg/l (1) |
Biological oxygen demand (BOD) mg/l |
18mg/l to
27mg/l |
<1.7 (1) |
Dissolved oxygen (DO) mg/l |
4.6mg/l to
8.8mg/l |
4.8mg/l (2) |
Hydrogen Sulphide (H2S) µg/l |
88ppm - 99ppm. (Total Sulphide In sediment pore water) |
2µg/l (2) |
Lead |
<1.3µg/l |
8.1µg/l (2) |
Chromium |
<.5 –
1.1µg/l |
50 µg/l (2) |
Copper |
<1.0µg/l |
3.1µg/l (2) |
Cadmium |
<1.0µg/l |
9.3 µg/l (2) |
1)
NRCA
Proposed Coral Reef Standard
2)
USEPA
Criterion Continuous Concentration(CCC)