Home |
MONITORING REPORT
Technological and Environmental Management Network Ltd
DREDGING AND RECLAMATION PROGRAMME IN
The R1 bund preparation
continues. First sector completed, material dredged from PB dredge site being
pumped into the completed section of R1 from the Leonardo Da
Vinchi. Significant
plume noted from the outlet weir in R1. Screen around outlet stolen, to be
replaced.
Hopper dredge Christofo Colombo dredging
in H1 and H2, material being disposed of at 1000m contour outside of the harbour. No problems
at the dump site here, but dredge site has significant plume, but no impact
noted at the Bustamante Beacon, near to the
.
Monitoring trips
were carried out on the following dates:
Thursday January 3rd: Site inspection at R1
Wednesday 16th
January: :Site inspection at R1, Water quality
monitoring of dredge activities
Saturday 19th
: Flight over dredge and disposal
sites
Photographs
attached.
No screens visible. At
R1
Water Quality
Monitoring Results
METHODOLOGY:
Samples were collected on January 16, and measurements of
TSS were made at the following sites
·
At
Middle Ground - Propeller wake of ship using channel
·
At H1 in wake of dredge
·
Bustamante
beacon
·
H1 approximately 40m after dredge had
passed
Data from the fixed stations for January 7 to 20 are
available.
RESULTS:
Results of
sample analysis are being prepared by the laboratory. Field
measurements made on January 16 [1]
indicated the following:
·
TSS in propeller plume of vessel was
determined to be in the range 0-180mg/l. The highest reading was recorded at
the bottom of the water column, while the lowest reading was recorded at 6m
below the surface.
·
At H1 in the plume of the dredge TSS
generally varied between 100 and 300mg/l.
·
At Bustamante
beacon the range was determined to be around 5mg/l throughout the water column.
Near the bottom an off scale reading was obtained. This was considered to be
due to disturbance of the seafloor by the probe/and or the sampler.
·
A resampling
in sector H1 about 40minutes after the dredge had passed indicated
significantly reduced TSS (5-50mg/l).
Data from the fixed stations indicate the following:
·
Very high TSS values at Middle Ground
Jan 7 to 8 (range 100->500mg/l).
·
Elevated TSS values at Angel and Bustamante between January 7, and 9 but significantly less
than Middle Ground. At Angel beacon TSS was determined to be in the range
30->500mg/l while at Bustamante beacon a range of
50-100mg/l was determined.
·
Subsequent to cleaning on January 11,
all fixed stations showed greatly reduced levels (range 0-20mg/l).
·
From January 12 to 13, TSS at Angel and
Bustamante remain in the range 0-5mg/l. Middle ground
however trended upwards going off scale (>350mg/l) by January 13.
CONCLUSIONS/ENVIRONMENTAL IMPACT
·
Dredging in H1 created a plume which
had TSS levels up to 30 times the criteria value.
·
The majority of material forming the
plume in the wake of the dredge is removed within forty minutes of dredging.
·
Disappearance of the plume is quite
likely a combination of settling and local currents.
·
WQ in the vicinity of Bustamante and Angel beacons continues to be relatively
unaffected.
·
Middle ground continues to be
relatively heavily impacted by TSS. Propeller wake appears to be a significant
contributor to episodes of
TSS.
·
Fouling of the sensors is a contributor
to the high TSS values observed particularly just before cleaning of the
sensors.
Table
1
Indicator Parameter |
Phase 1 Background Levels |
Standard/Criteria value |
Total suspended solids (TSS) mg/l |
0 -7 |
<10mg/l (1) |
Biological oxygen demand (BOD) mg/l |
18mg/l to
27mg/l |
<1.7 (1) |
Dissolved oxygen (DO) mg/l |
4.6mg/l to
8.8mg/l |
4.8mg/l (2) |
Hydrogen Sulphide (H2S) µg/l |
88ppm - 99ppm. (Total Sulphide In sediment pore water) |
2µg/l (2) |
Lead |
<1.3µg/l |
8.1µg/l (2) |
Chromium |
<.5 –
1.1µg/l |
50 µg/l (2) |
Copper |
<1.0µg/l |
3.1µg/l (2) |
Cadmium |
<1.0µg/l |
9.3 µg/l (2) |
1)
NRCA
Proposed Coral Reef Standard
2)
USEPA
Criterion Continuous Concentration(CCC)
Home |