|
|
|
4.3.2 EIA Notice.
Based on the assessment of the environmental impact indicated
by the Project Information Form, within 10 days of receipt of
the Form, NRCA might issue a notice requesting the Developer
to do an EIA. Every Developer so notified will have to submit
draft Terms of Reference to NRCA for approval.At this stage
the Developer will be given general guidelines for conducting
the EIA as well as sample Terms of Reference for similar projects
if any is available.
|
4.3.3 EIA Review
A draft EIA report (at least six copies) must be submitted to
NRCA for review and comments. A preliminary review of the draft
is done within ten working days to see if any additional information
is required. If additional information is needed this is requested
immediately. Upon receipt of the information the NRCA EIA Review
Committee will decide which external agency, if any, e.g. Port
Authority, the Environmental Control Division of the Ministry
of Health, Office of Disaster Preparedness, etc., must be asked
to review and comment on the document as well.
The Developer may also be granted an audience to full explain
any areas of the draft report that may not be clear enough
to the Review Committee.
The review process can take up to ninety days. At the end
of the NRCA inter-nal review the Developer may be granted
provisional approval to initiate the project with specific
conditions stipulated.
|
4.3.4 Public Notification.
Draft EIA reports are made available to the public at the NRCA
library, at local libraries, and at Parish Councils; and the
public is notified that an EIA report has been submitted, and
that thirty days are allowed for comment. Any comments received
from the public are brought to the attention of the Devel-oper
by the NRCA.
|
|
4.3.6 NRCA Assessment.
The NRCA will take into account any and all comments received
from the public and the concerned external government agencies
and give a final response to the Developer as to whether or
not his project is environmentally acceptable. The response
will summarise the findings of the review of the EIA report,
and indicate areas which need further attention, or impose con-ditions
for approval.
|
4.3.7 Appeals
In cases where a project is found to be environmentally unacceptable
and is not approved, the Developer may appeal to the Minister
with responsibility for the environment, against the decision
of the Authority within ten days after the date of the decision.
|
4.4 Schedule of Fees.
The fees payable to NRCA by Developers for being allowed to construct
and operate facilities within the coastal zone are gazetted under
The Beach Control Authority (Licensing) (Amendment) Regulations,
1955.
|
|
5. SITE
DATA REQUIRED FOR DETAILED DESIGN
For sound route planning, and detailed engineering design it is essential
to have the following range of site-specific data: |
5.1 Ecology -
Flora and Fauna
For projects of any appreciable size or scope NRCA will require
that appropriate site surveys be carried out to properly identify
existing marine ecosystems, and fully document the baseline conditions.
A typical checklist of data that will have to be provided will
include:
water quality, aquatic vegetation, critical habitat, spawning,
rearing and migration routes, threatened, rare or endangered species.
|
5.2 Sea-Currents
and Bathymetry
Normally, the information available on published navigation charts
concerning sea-currents and water depths will not be adequate for
detailed route planning. Project sponsors will have to be prepared
to carry out appropriate current studies and hydrographic surveys
in order to be able to prepare site-specific charts showing local
current patterns and existing seabed contours at suitable intervals.
|
5.3 Meteorology
Site-specific data on rainfall, wind, waves and tides will be required.
Usually, much useful data on these matters can be obtained from
the Government Meteorological Office.
|
5.4 Seabed Soils
It will be essential to have a good appreciation of the nature of
the seafloor soils. Normally, sufficient qualitative information
can be obtained from grab samples and probes. However, if any trenching
of the seabed to bury pipe-lines or cables is contemplated, boreholes
will have be drilled, and appro-priate sampling and testing carried
out to determine stratification.
|
5.5 Geomorphology
Project sponsors should take all necessary steps to ensure that
appropriate investigations are carried out to clearly identify whatever
geomorphological processes might be actively in force at a chosen
locality, so as to be able to take such factors into account in
the engineering of the project.
|
5.5.1
For example, along many stretches of the islands south coast
-from Cow Bay in the east to Sav-la-mar in the west, there is
active progradation, accretion and erosion taking place
at the shoreline, (refer to P.A. Wood, in Journal of the Geological
Society of Jamaica, Vol. XV, 1976).
Progradation refers to the advance of the shoreline resulting
from nearshore deposition of sediments brought to the sea by rivers.
Accretion refers to beaches that are accumulating due
to inflow of sediment from external sources other than nearby
rivers.
Beach Erosion refers to the removal of material from
the shoreline due to wave action.
Any man-made facilities that are introduced into these areas
of the coastal zone will inevitably interrupt the on-going natural
processes and could result in unintended complications. For
instance, if a pipeline or cable is laid upon the seafloor at
a location where progradation or accretion is taking place,
the pipeline/cable will obstruct the natural regime of sediment
transport and could result in the rapid formation of dunes or
sandbanks that could drama-tically alter the nearshore environmental
conditions. Also, if pipelines/cables are installed at sites
where there is continuing erosion, they might eventually become
exposed and lose bearing support to the extent that the structural
stability and integrity of the facilities are negatively affected.
|
|
6.
ENGINEERING DESIGN CONSIDERATIONS FOR PIPELINES AND CABLES IN THE
COASTAL ZONE
Traditionally, engineers were trained primarily to respond to the
task of applying technical knowledge in the design, construction
and operation of systems that were intended to produce goods and
services for mankind, in the most economic and efficient
manner. In more recent times however, it has become clear that many
industrial practices that in the past were deemed to have been economic
and efficient, were actually environmentally destructive, and therefore,
in the longer term, truly uneconomic.
And so, currently, the practicing engineer is constrained, not
only by increas-ingly conservative regulations, but often also
by his own heightened profes-sional sensitivity, to pay careful
attention to the external effects of his works, and to strive
to ensure that his projects are environmentally sustainable, i.e
will not cause continuing environmental degradation.
|
6.1 Site Selection
is Paramount
The siting of a facility relative to the coastal zone may be of
greater concern than the type of project itself, since location
frequently can be the most signi-ficant factor in regard to the
seriousness of the impacts that are delivered to the receiving environment.
The following are some basic siting guidelines:
|
6.1.2 Avoid sites that are especially vulnerable to natural hazards
such as earthquakes and hurricanes. (Refer to the Geological Survey
Departments hazard maps).
|
6.1.3 Avoid locating facilities in areas where there is evidence
of shoreline and seafloor instability. (Refer to Geological Survey
Department).
|
6.1.4 Selection of a route for a pipeline or cable is often dictated,
to some extent, by factors such as the coastal topography, shoreline
configuration, and the location of any existing onshore facilities
to which the lines or cables are to be connected. However, the
main objective in route selection is to avoid obstacles and to
find the smoothest route to the desired water depth, maintaining
as straight a course as possible.
|
6.2 Pipeline Materials
Selection of the most appropriate type of material is a very important
part of the process of designing submarine pipelines. In choosing
the type of material for a pipeline, the following are the most
important aspects that engineers should evaluate:
|
6.2.1 Durability:
The material must be able to last in the extremely corrosive
marine environment.
|
6.2.2 Joint Strength:
If the material uses mechanical joints, the joints themselves
will be the weakest links in the pipeline system, and thus will
impose certain limitations in regard to the range of construction
methods that can be used to install the line.6.1.1 Avoid routing
of pipelines and cables through ecologically or archae-logically
sensitive areas
|
6.2.3 Joint Tightness:
Pipeline joints need to be leakproof, especially when carrying
pressurized liquids and gases. Properly welded joints are more
reliable than mechanical joints.
|
6.2.4 Flexural Ability:
The material must be able to flex without causing structural
failure, because if the seabed is uneven the line will have
to span across the low areas.
|
6.2.5 Resistance Impact/Puncture to
The material must be tough enough to be able to withstand accidental
impacts from boats, anchors, etc.
|
6.2.6 Resistance to Abrasion
The pipeline might be unintentionally scrubbing the seafloor
at times, due to wave or current action, and therefore the material
could be subject to abrasive forces which could cause serious
damage,
|
6.2.7 Requirement for Bedding
Pipelines made of material that is not strong enough to span
across irregularities of the seafloor, will require special
route preparation and bedding, which can be expensive.
|
6.2.8 High-Pressure Capability
For some usages, e.g. in the oil and gas industry, pipelines
will have to be capable of sustaining high operating pressures,
externally as well as internally; therefore the pipe material
must be high strength.
|
6.2.9 Flexibility of Construction
In deciding upon the type of material that may be the most suitable
for a project, very often, the criterion that is the most influential
upon the decision, is the question of the ability of the
material to allow a wide range of options in the choice of construction
methods.
|
6.2.10
Table 3 below gives comparisons of the qualities of some of
the more commonly used pipeline materials in terms of some selected
performance criteria.
|
Table 3. Comparisons of the Qualities of
Some Commonly Used Types of Pipeline Materials. |
|
Coated
Steel |
Cast
Iron |
High Density
Polyethylene |
Fibreglass |
PVC |
Reinforced
Concrete |
Resistance
to Corrosion |
Excellent (with
Cathodic
Protection) |
Good |
Excellent |
Excellent |
Poor |
Excellent |
Joint
Strength |
Excellent
(when welded) |
Fair to Poor |
Fair |
Fair |
Fair |
Poor |
Joint
Tightness |
Excellent
(when welded) |
Fair to Poor |
Good |
Good |
Good |
Poor |
Flexural Ability |
Good |
Fair to Poor |
Excellent |
Excellent |
Excellent |
Poor |
Resistance to
Impact/Puncture |
Excellent |
Fair to Poor |
Poor |
Poor |
Poor |
Excellent |
Resistance to
Abrasion |
Excellent |
Excellent |
Poor |
Poor |
Poor |
Excellent |
Requirement
for Bedding |
Good |
Fair to Poor |
Poor |
Poor |
Poor |
Poor |
High-Pressure
Capability |
Excellent |
Poor |
Fair |
Fair |
Fair |
Poor |
Flexibility of
Construction |
Excellent |
Poor |
Fair to Poor |
Fair to Poor |
Fair to Poor |
Poor |
Relative Cost |
Good |
Poor |
Good |
Good |
Good |
Excellent |
|
|
|
|
|
|
|
OVERALL
ATTRACTIVENESS |
Most Useful |
Very
Limited
Usages |
Limited
Usages |
Limited
Usages |
Very
Limited
Usages |
Very
Limited
Usages |
USAGES |
Used for
everything:
Oil & Gas,
Sewage
Outfalls,
Water. |
Formerly Used
for Water &
Sewage,
but hardly
used
anymore
|
Becoming
popular for
non-pressurized
usages, e.g.
for power
station cooling
but hardly
used anymore |
Becoming
popular for
non-pressurized
usages, e.g.
for power
station cooling
but hardly
used anymore |
Becoming
popular for
non-pressurized
usages, e.g.
for power
station cooling
but hardly
used anymore |
Too heavy.
Sometimes
used for
sewage
outfalls. |
6.2.11 The comparisons made in Table 3 above indicate that coated
steel is definitely the most versatile and useful material for submarine
pipelines. Although steel in seawater is very susceptible to corrosion,
experience in the oil and gas industry and the water supply industry
has shown that a well-coated pipeline with proper cathodic protection
will last for a very long time. Because of the need to protect steel
from corrosion, steel pipe is likely to be more expensive than concrete
or plastic. But construction costs are usually lower when steel is
used, because steel is readily adaptable to more construc- tion methods,
and thus allows greater construction flexibility. However, the real
economy from steel pipe usage lies in its adaptability to rapid fabrication
and installation, the reliability of radiographically tested welded
joints, and the inherent structural strength of steel.
|
6.3 Cable Materials.
|
6.3.1 Telecommunications Cables.
Modern telecommunications cables consist of a "transmission
core" of glass fibers, with outer layers of various types
of materials to strengthen, insulate and protect the fibers. (See
Fig. 1).
The degree to which cables need to be protected depends upon
the nature of the underwater environment. There are more hazards
to cables in shallow-water environments such as coastal zone
shelfs, than to cables that are deeply submerged upon the ocean
floor. Deep-water cables do not need armouring. Shallow-water
cables are given varying levels of external armour, (typically
tapes or wires). Cables canbe classified according to their
applications and the degree of armouring as follows:
|
6.3.1.1 Deepwater (DW) Cable.
Consists of the transmission core, composite power conductor,
and an outer encasement of polyethylene insulation.
|
6.3.1.2 Special Applications (SPA) Cable.
This configuration consists of the basic DW cable, with additional
protection provided by a longitudinal metallic barrier covered
with a high density poly- ethylene protective layer. This type
of cable is suitable for use in areas where it might be subject
to abrasive forces, where fish might gnaw upon it, and at locations
where cables are to be joined.
|
6.3.1.3 Light Wire Armour (LWA) Cable.
In this configuration the basic DW cable is given a single layer
of medium strength armour wires. This type of cable is usually
for burial in deep waters.
|
6.3.1.4 Single Armour (SA) Cable.
SA cables are very similar to LWA cables, but because this cable
is not buried, the outer protective layer is made of thicker
wires than those used for the LWA cables.
|
6.3.1.5 Double Armour (DA) Cable.
DA cables are for use in shallow, nearshore waters, where there
is high risk of impact and abrasion damage. This type consists
of the basic DW cable with two layers of protective steel wire.
|
|
6.3.1.1 HPOF Installations.
In HPOF pipe-type systems, three cables, comprising a circuit,
are installed in a steel pipe.
|
6.3.1.1.1 Each cable consists of a stranded copper or aluminium
conductor with an electrostatic conductor shielding, many layers
of oil-impregnated paper tape, insulation shielding, moisture
seal and a helically wound skid wire. The wire serves to protect
the cable from mechanical damage during installation. Each individual
cable is typically 2 to 5 inches in diameter.
|
6.3.1.1.2 The steel pipe provides protection for the cables
from mechanical damage, and prevents the entrance of moisture,
as well as providing a housing for the pressurizing oil which
fills the remaining space in the pipe.
|
6.3.1.1.3 The inside diameter of the pipe must be roomy enough
to allow the three cables to be pulled in without jamming. In
HPOF systems, the distances between pressurizing stations is
limited to around 2 kilo-metres, because, in practice, this
is the maximum distance that the cables can be pulled into the
pipe once it is installed.
|
6.3.1.1.4 To protect the pipe against corrosion, various types
of coatings are applied to its external surface. The coating
materials may be asphaltic mastic, coal tar enamel, polyethylene
or polypropylene. Also, cathodic protection is usually provided
in submarine installations.
|
6.3.1.1.5 HPOF pipe-type systems require external encasements
of concrete to reduce buoyancy and provide additional protection
for the pipe.
|
6.3.1.2 LPOF Installations
Unlike the HPOF cable, which requires field-installed pipe for
cable protec-tion, the LPOF cable is complete as it leaves the
factory and is therefore called "self-contained". The
cables may be either directly buried or installed in ducts. Self-contained
cables can be obtained in either single or triple-con- ductor
design.
|
6.3.1.2.1 The LPOF cable is made of an annular shaped conductor
of stranded aluminum or copper. Like pipe-type cables, self-contained
cables utilize layers of oil-impregnated paper tape for insulation.
The diameter of the cable depends upon the design voltage.
|
6.3.1.2.2 The cavity in the center of the conductor is filled
with oil under pressure. The oil penetrates into the paper insulation
through small openings and together they furnish the necessary
dielectric strength. To assure complete saturation of oil at
all times, the cable is shipped and stored on reels equipped
with oil pressure reservoirs.
|
6.3.1.2.3 The insulation is covered with an extruded lead or
aluminium sheath which contains the insulating oil in the system
and prevents moisture penetration. Metal tapes are applied over
the sheath to give it addi-tional mechanical strength. A polyethylene
jacket is extruded over these tapes. For submarine installations,
armouring in the form of steel or aluminum alloy wires is applied
to the cable.
|
6.3.1.2.4 LPOF self-contained and extruded dielectric cables
are well-suited for underwater use because of their flexibility,
because they are delivered ready to be installed, and because
they can be manufactured and installed in long lengths.
|
6.4 Loadings
on Submarine Pipelines
During fabrication, construction and operation, a pipeline can assume
many configurations and resulting states of stress. The various
structural functions that a submarine pipeline can assume include:
tension member, compression member, suspension member, pressure
pipe, and externally loaded cylinder. Each of these con-ditions
must be investigated and addressed, in order to assure the integrity
and stability of the installed pipeline.
Submarine pipelines have to be designed to withstand the range of
static and dynamic loadings due to forces from gravitational influences,
environmental factors, construction techniques, and operational
conditions:
|
6.4.1 Gravitational influences are static and include the weight
of the pipe, corrosion coatings, weight coatings or anchor blocks.These
loads may be adjusted for the buoyancy of the sea water or the buoyancy
force may be considered as an additional loading.
|
6.4.2 Environmental loadings are derived from sea currents, wave
action, sedimen-tation processes and seafloor variations. Environmental
forces are dynamic, not readily quantifiable, and therefore can
present challenges to the designer as to how to assess their influence
on the pipeline.
|
6.4.3 If a pipeline is buried, many of the factors influencing stability
become less important. However, the type of seafloor soils, the
strength of sea-currents, and the regularity of the seabottom, are
very significant factors in relation to the possibility or likelihood
of scouring around the pipe.
|
6.4.4 If the sea-bottom is uneven, the pipeline will span across
the depressions, and the hydrodynamic forces created by sea currents
passing over (and under) the exposed pipeline can cause vortex shedding,
which can have such forceful effects upon the pipeline itself as
to cause sliding and lift-off.
|
6.4.5 The designer of a pipeline needs to know the methods and techniques
that will be used to install the pipeline. Different installation
methods will impose different configurations on the pipeline, resulting
in different sets of construc-tion forces and stresses.
|
6.4.6 The loadings that are imposed when a pipeline is in use come
from internal pressure, surges, external pressure and support conditions.
Internal pressures and surges in a submarine pipeline are no different
from those that would occur in a similar land-based pipeline, and
therefore do not pose any special problems for designers. External
(hydrostatic) pressures are also quantifiable without any great
difficulties. However, assessment of conditions of support can be
challenging, due to questions such as whether the pipeline will
be exposed, or buried, or spanning in places. And support conditions
can change over time, due to storm action, or on-going littoral
processes.
|
7. ENVIRONMENTAL
IMPACT ASSESSMENT
Project sponsors are advised, that prior to embarking upon the
preparation of their EIA, they should seek to develop and agree
appropriate Terms of Refer-ence with NRCA. Typically, Terms of Reference
should include at least the following information:
|
7.1
General Description of the Project and its Objectives |
§ background information identifying
the need and justification for the project.
|
§ description of the main features
and activities of the project, and identification of the construction
and operation processes that will pose risks to the environment
or generate positive impacts.
|
§ the anticipated timing of the
project and schedule of the performance of the main construction
activities.
|
7.2
The Existing Environment of the Project Area.
|
§ the physical environment
|
§ the biological environment
|
§ the socio-economic and cultural
environment
|
Baseline data should include:
|
¨ Water quality at high and low tides.
Water samples should be tested for Suspended Solids, Coliforms,
Nitrates, Phosphates, and other parameters as may be deemed neces-sary
in relation to the particular purpose of the pipeline or cable that
is to be installed;
|
¨ Water depths, bottom conditions,
currents. Water circulation patterns are to be evaluated in the
context of the capability of the water body to flush itself;
|
¨ Identification of the existing pattern
of coastline dynamics - i.e. determination of the prevailing pattern
of littoral transport whether the shoreline is stable, or prograding,
or accreting, or eroding;
|
¨ Full descriptions of the condition
of any existing natural resources, e.g. seagrass, mangroves, coral
reefs. Particular attention should be paid to sedimentation, algal
growth, patterns of live and dead coral, and structure of fore and
back reefs.
|
|
7.3 The Relevant Legislative and Regulatory Framework.
Project Sponsors will be required to include in their EIA report,
a section describing all relevant Jamaican legislative enactments,
environ-mental policies, Standards and Regulations; and should identify
the appropriate authority jurisdictions that will apply to the project.
|
7.4 The
Anticipated Environmental Impacts
The EIA report should contain descriptions of the anticipated direct
and indirect effects of the construction and operation activities
of the project. In identifying the likely environmental effects
of the construction and operation activities, it would be helpful
for project sponsors to analyze them in terms of the following terminology:
|
§ adverse effect: an effect
that is large in magnitude and has important con- sequences. Both
of these characteristics (i.e. large magnitude and importance)
must be present, in order for the effect to deserve to be termed
adverse.
|
§ cumulative effect: an effect
that gives an incremental rise in the level of an impact, when added
to other past, present and reasonably forseeable activities. Cumulative
effects can result from individually minor but collectively significant
activities taking place over a period of time.
|
§ triggering effect: an effect
that induces other indirect effects. These effects are not directly
generated by (the instant) project activities, but they develop
because the project came into being.
|
7.5 Monitoring
and Mitigation Plans for the Construction Phase and for the
Operational Phase |
7.5.1 The EIA should include detailed plans for monitoring and mitigating
any adverse effects that might arise during construction or operation
of the facilities. Any mitigatory measures recommended should be
technically feasible and cost-effective, and should result in reduction
of the negative effects to tolerable levels.
|
7.5.2 Wherever possible, estimates of the financial and economic
costs of the potentially degrading effects that the project might
have upon the environment, and the costs of the mitigatory measures
proposed, should be included in the EIA.
|
7.6 Contingency Plans.
|
7.6.1 Contingency plans should be presented for dealing with any
emergencies that could arise during the construction or operation
phases of the project, such as fire, explosion, or accidental spillage
of petroleum products or other hazardous/toxic materials. The appropriate
response to leaks, breaks, explosions, fire and the resulting loss
of fluid, will vary according to the toxicological and physical
properties of the spilled material and the potential impact it may
have upon public safety and the environment.
|
7.6.2 To ensure the effectiveness of contingency planning, properly
trained personnel and suitable equipment must be available. Project
sponsors should therefore include in their EIA, information concerning
plans for providing appropriate training and equipment for the personnel
who will be involved in dealing with the types of emergency situations
that could arise.
|
7.6.3 In developing contingency plans for dealing with emergencies,
it will be useful for Developers to seek consultations with the
Coast Guard of the Jamaica Defence Force, and also with the Office
of Disaster Preparedness and Emergency Management, since in anycase,
NRCA will refer any contingency plans to those Agencies for comments,
and any comments received from those Agencies will be given careful
consideration by NRCA in making decisions as to the suitability
of any contingency plans submitted.
|
8. THE CONSTRUCTION PHASE
|
8.1 Developers
Will be Required To Monitor Construction and Submit Reports
to NRCA at Prescribed Intervals |
8.1.1 Throughout the construction phase of their projects, Developers
will be required to maintain continuing effective liaison with the
concerned government regulatory Agencies and local communities,
and to ensure that any issues or concerns that might arise during
this phase, are clearly understood and appropriately dealt with.
|
8.1.2 The particular construction activities which will require
monitoring as the work progresses will have been identified in the
EIA report. Each Construction Permit issued by NRCA will indicate
the required frequency for submission of written reports from the
Developers to NRCA.
|
8.2
Methods and Equipment for Laying Pipelines
The main factors that influence the methods and types of equipment
that are used to install submarine pipelines are: the nature of
the pipeline material itself; method of jointing; weight, size,
flexibility; depth of water; velocity of sea currents; type of substrate;
availability of equipment.
Pipelines hundreds of kilometres in length have been installed
in waters over a thousand metres in depth for the oil and gas
industry in the Gulf of Mexico and other parts of the world. Such
installations are carried out by purpose-built lay barges together
with attendant unmanned mini-subma-rines ("Remotely Operated
Vehicles", ROV's), and are designed and supervised by specialist
engineers. Such types of projects are outside the scope of these
guidelines.
The main types of pipelines, (by different usages), that are
found in the coastal zone are: oil and gas, freshwater,
sewage outfalls, and cooling water intake and discharge lines.
The following are some of the methods and types of equipment that
are commonly used to lay these pipelines:
|
8.2.1 Conventional Laybarge, (S-lay).
The conventional laybarge is by far the most common method of
installing welded steel pipelines -whether for oil, gas, fresh-water
or sewage outfall.
Under this method, standard lengths of pipe are jointed up sequentially
at a series of welding stations aboard a long deck barge. The
jointed-up por-tion of pipeline passes through the stern of the
vessel onto an extended cradle called a "stinger". The
stinger prevents the pipe from being over-stressed as it passes
through the stern and curves downward into the sea. The pipeline
undergoes a second bend as it comes to rest on the seafloor. The
two bends give the pipeline an "S" shaped configuration
as it is instal-led. In S-lay operations, pipelines can extend
over 300m from the vessel, but whenever such lengthy extensions
are done several tensioning and anchoring systems employing long
cables have to be applied to the pipeline to keep it from becoming
damaged through overstress.
|
8.2.2 Reel Method
Reel laying is used for fast laying of small pipelines of up
to around 300mm diameter. Under this method, the standard lengths
of pipe are jointed up ashore and fed onto a reel of up to 13m
diameter. The reel is then mounted horizontally on a barge or
ship that uses the S-lay method of installation.
|
8.2.3 Bottom Assembly
This method consists of assembling relatively short lengths of
pipes (say up to around 100m) on the seabed, using barge-mounted
cranes, and then connecting up the pieces underwater by divers.
This method becomes impractical in water depths of over 100m.
|
8.2.4 Bottom Pull
The bottom pull method entails pulling lengths of pipeline that
have been jointed up onshore into place on the seafloor along
the alignment that the pipeline is intended to finally rest. The
jointed-up pipeline lengths, (gen-erally up to around 500m at
a time), are set on skids ashore, parallel to the route of the
pipeline. A flat barge with a sufficiently powerful pulling winch
mounted on deck is then anchored several hundred metres offshore,
directly in line with the final route on which the pipeline is
to be laid.
To commence installation, the pull cable is unreeled from the
winch of the pull barge, taken ashore along the intended route
of the pipeline, and attached to the leading end of the line that
is to be pulled into place. This first length of pipeline is then
pulled into alignment on the seafloor, and as the back end reaches
the shoreline, pulling is halted, so that the next length of pipe
can be put into place onshore and connected to the back end of
the section that is already on the seabed. Pulling is then resumed
and the process repeated until the total required length of pipeline
is in place.
|
8.2.5 Surface Pull
This method is essentially the same as the bottom pull method
except that in this case the pipeline has to be light enough to
float when empty, either by virtue of its own inherent lightness,
or by having buoyancy elements attached. As soon as it is pulled
onto alignment, water is allowed to enter the pipeline and sink
it into place.
|
8.3 Methods
and Equipment for Laying Cables
Submarine cables are currently providing linkages in many of the
world's important intercontinental telecommunications systems. Also,
in many developed countries, subsea cables are in use for transmitting
electrical power across waterways, from one region to another.
The work of installing these trans-oceanic cables is performed
by means of specially designed ships that povide highly maneuverable
platforms loaded with sophisticated equipment for placing, pulling,
jointing, coupling, and testing, the cables.
A general outline is given below of how cable laying in the
coastal zone is usually done.
|
8.3.1 The first cable section to be installed is the shore end.
The cable ship or barge is anchored some distance offshore and the
end of the cable facing the shore is pulled from the floating vessel
towards a preconstructed man-hole on land near the shoreline. For
safety and protection, the near-shore section of the cable almost
always has to be buried -at least where it passes through the surf
zone. The cable is then secured inside the shore manhole and spliced
to the previously installed land cable. This section of cable is
then tested to confirm that the integrity of the insulation and
the transmission characteristics of the cable itself are unimpaired.
Installation of the deep-water segment of the system begins after
the shore-end testing is completed.
|
8.4
Methods and Equipment For Burying Pipelines and Cables
It is usually necessary or desirable to bury at least the inshore
sections of pipelines and cables, giving a metre or more of cover.
This is done for one or more of the following reasons:
§ to protect them from destructive
wave action;
§ to protect them from boat/ship/anchor
damage;
§ to avoid instability due to bottom
currents;
§ to allow unimpeded recreational
use of beaches.
A number of the more common methods and types of equipment used for
excavating trenches for burying pipelines and cables are described
below.
|
8.4.1 Clamshell and Dragline
In shallow water close up to the shoreline it is feasible to use
clamshell and dragline dredgers to excavate and backfill. Trenches
in the surf zone tend to get backfilled quickly by wave action
and therefore it is necessary to plan and schedule the laying
in this area especially carefully so that the operation can be
carried out swiftly. Sometimes it may even be cost-effective to
install temporary sheetpiles along the sides of the trenching
in order to minimize excavation and backfill.
|
8.4.2 Stationary Cutter Suction Dredge
This type of machine can only operate where water depth is greater
than around 4m. Cutter suction dredges are effective for removing
even the harder types of bottom material, but they cannot operate
in rough sea conditions.
|
8.4.3 Trailing Suction Hopper Dredge
This type of machine can dredge down to as much as 40m, and can
operate in rougher sea conditions than the cutter suction; but
it can only cope with the relatively softer types of seabed material.
|
8.4.4 Marine Plow
Towed plows have been used for digging trenches up to around 2m.
deep -even in stiff clay.
|
When dredging machines such as those mentioned above are used
for excavating trenches, the trenching is usually done before
the pipeline or cable is laid. The plow, however, is more often
used to cut trenching after the pipeline or cable is laid,
thereby providing a guide for the alignment of the plowing.
If the bottom material is relatively soft clay, sand or silt,
a jet sled can also be used for post-installation burial of
pipelines. The sled is in the form of a fork that straddles
the pipeline and blasts out high velocity jets of water that
penetrate and loosen the material on both sides of the line,
spreading the arisings on both sides of the trenching. The sled
is pulled along by a surface barge, that carries the large pumps
and prime movers required to power the water jets. As the sled
is pulled along, the pipeline settles into the trench behind
it.
|
|
8.4.7 Backfilling Trenches
Some nearshore trenches will tend to become sandtraps, and
be naturally backfilled, if they are located in the surf zone,
or where there is a heavy littoral drift crossing the line.
But trenches in deeper water sometimes will not backfill naturally,
and the pipeline or cable in the bottom of the trench, though
lowered below the general level of the seafloor, will not be
fully protected. In cases like this, for full protection, the
trenching will have to be actively backfilled.
|
8.5
Mitigation of the Potentially Harmful Effects That Might Occur
During Laying and Burial of Pipelines/Cables in the Coastal Zone
In the Table 4 below some of the more harmful effects that might
come from the construction processes required for installation of
pipelines and cables in the coastal zone are identified, and some
appropriate mitigation measures suggested.
|
Table 4 - Some Mitigatory
Measures for Potentially Harmful Environmental Effects That
Might Occur During Installation of Pipelines and Cables In
the Coastal Zone. |
Potential Negative Impacts |
Mitigating Measures |
1. Project location may affect sensitive
habitats and/or valuable fisheries resources or otherwise significantly
degrade environmental quality.
|
1. Perform screening
analysis of site environs and ecology and select an area that is not
adjacent to sensitive habitat and would not
displace valuable fisheries resources. |
2. Unintended removal or disturbance of precious
flora or fauna in areas where they are indigenous. |
2. Have divers double check along the proposed
route for the presence of any rare, threatened or
endangered species |
3. Increased short-term turbidity due to excavation
and backfilling dur ing burial of pipelines/cables
|
3. Reduce turbidity by efficient use of less intrusive
trenching methods (e.g. thrust boring, directional
drilling), and scheduling of trenching to coincide with
low current flow periods. |
4. Covering of valuable benthic species (e.g. mussels,
clams) by sediment.
|
4. Monitor turbidity and maintain sediment concentrations
within tolerable limits (to be agreed with NRCA in
relation to the particular species at risk). |
5. Interference of floating construction plant
with other maritime traffic.
|
5. Prepare a program in advance to co-ordinate
and reduce interference to other waterway
users. |
6. Damage to archaelogical treasures and artifacts
due to excavation and backfilling of trenches.
|
6. In areas where it is historically not unlikely
that archaelogical treasures might be found,
(e.g. Port Royal, Seville), engage divers
to constantly monitor the underwater work. |
7. Objectionable high noise levels such as to cause
disturbance to nearby residents. |
7. Reduce noise level by decreasing operating level
during quiescent periods in the local community. |
9. THE OPERATIONAL PHASE
|
9.1
Monitoring of Pipelines and Cables During the Operational Phase,
and Reporting to NRCA.
|
9.1.1 Throughout the operational phase of a project, the project
sponsors will be required to maintain continuing effective liaison
with the concerned gov-ernment regulatory Agencies and local communities,
and to ensure that any issues or concerns that might arise during
this phase, are clearly understood and appropriately dealt with.
|
9.1.2 The particular activities and processes which will require
monitoring dur-ing the operational phase will have been identified
in the EIA report. Each Operating Licence that is issued by NRCA
will indicate the required fre-quency for submission of written
reports from the Developers to NRCA.
|
9.1.3 NRCA recommends that at the time of submission of application
for licence to operate, the operators of pipelines and cables in
the coastal zone should name an individual who will be responsible
on behalf of the project sponsors for ensuring that the operators'
responsibilities to NRCA and the public, for protecting the environment,
will be adequately fulfilled.
The individual who is appointed to be the operators' Environmental
Compliance Officer, shall be suitably qualified for the
post, and his/her specific functions in relation to NRCA shall
be as follows:
§ to oversee on a continuing day-to-day
basis, the collection of data and documentation of all site activities
relating to environmental matters;
§ to prepare the environmental monitoring
reports called for in the approved Monitoring Plan, and submit
them to the NRCA at the prescribed time intervals;
§ to be available to the NRCA at
all times for consultations regarding any environmental issues
that might arise con-cerning operation of the pipelines or cables.
|
9.1.4 Records of the following information should be maintained
at site for operation and maintenance purposes:
|
9.1.4.1 Detailed "As Built" drawings of all pipelines
or cables and all ancillary facilities;
9.1.4.2 Route maps and accurate data defining vertical and
horizontal alignment of the installed pipelines or cables;
9.1.4.3 Specifications for the particular coatings and/or cathodic
protection systems;
9.1.4.4 Pressure test data;
9.1.4.5 Previous inspection reports;
9.1.4.6 Necessary operational data;
9.1.4.7 Records of past failures and repairs;
9.1.4.8 Records of inspection and maintenance of safety and
emergency response equipment.
|
9.2
Maintenance and Mitigation of the Operational Impacts of Pipelines
in the Coastal Zone
Operators of undersea pipelines will be required to implement appro-
priate inspection, maintenance and mitigation procedures while their
facilities are in use, so as to minimize the risk of damage to the
environ-ment, injury to personnel and threats to public safety.
The types of main-tenance and mitigation procedures required will
depend upon factors such as the pipeline material, its location
in relation to sensitive habitats, whether buried or exposed, depth
of water, bottom conditions, and the characteristics of the fluid
being transported.
|
9.2.1 Oil and Gas Pipelines
Oil and gas pipelines are usually made of steel, with welded joints.
They are normally coated for corrosion resistance and may also
have cathodic anodes attached for added protection. Larger size
pipelines will have con- crete encasements to counteract bouyancy
and to protect the pipeline from mechanical damage.
|
9.2.1.1 Operators of undersea pipelines will be required to
establish and maintain appropriate underwater surveillance programs
to detect leaks, encroachments, and any other conditions along
the route that may affect the safe operation of the pipeline.
9.2.1.2 Written procedures should be established for start-up,
operation, and shutdown of the pipelines, and these procedures
should be scrupulously adhered to. Procedures should outline
preventative measures and system checks to ensure the proper
functioning of protective and shutdown devices and of safety,
control, and alarm equipment.
9.2.1.3 Pipeline systems should be operated so that the calculated
pre-determined operating pressures are not exceeded. Over-pressure
protection devices should be set to ensure that the maximum
operating pressure (MOP) is not exceeded by more than 10% during
surges and other deviations from normal operations.
9.2.1.4 Communications equipment should be installed and maintained
as needed for proper pipeline operations under both normal and
emer-gency conditions. In the event of an emergency, pipeline
operators should immediately notify NRCA, the Jamaica Defence
Force Coast Guard, and the Office of Disaster Preparedness and
Emer-gency Management.
9.2.1.5 Any necessary pipeline repairs should be performed under
quali-fied supervision by trained personnel who are fully conversant
with the maintenance plan and operating conditions of the pipeline,
the companys safety requirements, and the hazards to employees,
the public and the environment.
9.2.1.6 A written emergency plan should be established for implementa-tion
in the event of system failure, accident, or other emergency,
and should include procedures for prompt and expedient remedial
action to safeguard personnel and limit the discharge from the
pipeline system.
|
9.2.3 Sewage Outfall Pipelines
|
9.2.3.1 Sewage outfall pipelines, like hydrocarbon lines, are
also most often made of steel; but unlike gas and oil pipelines,
they usually operate under gravity flow, with much lower internal
pressures, and therefore if leakages develop, the discharges
will not be as potentially impactful as those from pressure
pipelines.
9.2.3.2 Outfall pipelines are installed for the purpose of conducting
effluent out to a location in the sea where effective dilution
and dispersion can be achieved. The diffusers that are usually
installed at the ends of outfall lines are the elements that
require the most monitoring and inspections to ensure that they
are functioning properly. Diffusers have to be regularly cleaned
to remove accu- mulated grease, slime and grit. Cleaning can
be accomplished through flushing of the line.
|
9.3
Maintenance and Mitigation of the Operational Impacts of Cables
in the Coastal Zone
The great majority of faults that occur during the operating lifetime
of modern telecommunications and electricity cables installed in
the rela-tively shallow waters of the coastal shelf are caused,
not from inherent material failures, but by physic-al damage from
external sources such as dredging operations, fishing equipment,
boat anchors, fish gnawing and abrasion from scrubbing on hard seafloor.
Although the impacts that are delivered to the marine environment
as a result of normal operations of the cables are not usually seriously
degrading, nevertheless submarine cables must be monitored and inspected
regularly in order to ensure that appropriate maintenance and mitigatory
measures are applied whenever called for.
|
9.3.1 Telecommunications Cables
9.3.1.1 For repeatered undersea systems, because of the high
voltages involved, the main operational hazard is electrical
safety. To mitigate this hazard, all high-voltage elements in
these types of systems must be equipped with key interlocks,
which prevent access to hazardous voltages; and cable repairs
should not be conducted on cables that are energized.
9.3.1.2 Typically, repairs done by ship are both random and
infrequent, and therefore in some regions it is common industry
practice for several system owners to share a repair ship,
key repair personnel, tools and other maintenance resources.
This arrangement allows rapid, cost-effective response to
system failures.
|
9.3.2 Electricity Transmission Cables
9.3.2.1 A few of the more common causes of failure of submarine
electricity transmission cables are:
§ impact from dredging equipment,
from anchors, from commercial fishing equipment, from bottom
abrasion;
§ breakdown of electrical insulation
from thermal, electrical or mechanical stress;
§ defects in manufacture or
installation.
|
9.3.2.2 Cable failures frequently result in explosive electrical
short circuits within the system, which can cause significant
damage. The short circuits are short-lived, since the installation
is protected with circuit breakers which open automatically
to stop the flow of current within a fraction of a second.
|
9.3.2.3 Once a failure is detected, the exact location of the
damage must be pin-pointed. Some sophisticated techniques and
equipment have been developed for use in locating cable defects,
but very often human divers have to be called upon to find the
exact locations of cable faults. Once the fault is located,
that portion of the cable is isolated from the rest of the system
by closing particular valves which would have been installed
at strategic points along the cable for emergency purposes.
|
9.3.2.4 Failure of HPOF pipe-type and LPOF self-contained systems
results in the leakage of insulating oil in cases where the
pipe or cable is actually ruptured. The HPOF systems have the
potential for greater damage than LPOF, because of the greater
quantity of oil and the higher pressures that are maintained
in these systems. The oils used are of varying viscosities and
of relatively low toxicity. When spilled, they tend to flow
easily and disperse. (HPOF and some LPOF oils are usually biodegradable).
|
9.3.2.5 In some cases, when relatively small leaks develop in
submarine cables, operators tend to keep on pumping, to maintain
a slight positive pressure. This procedure is used to protect
the cable system from further damage by preventing contaminating
matter such as sand or water from entering through the damage
break. While continuation of pumping will result in a greater
discharge of oil into the surrounding waters than if pumping
is completely stopped, continuation of pumping is probably more
environment-ally friendly because it may save a cable installation,
and thereby avoid the cost, time and environmental consequences
of having to pull in a new cable.
|
10. OPTIONS
FOR ABANDONMENT OF PIPELINES AND CABLES.
Project sponsors should include in their project planning, consideration
of options regarding de-commissioning, dismantling or abandonment
of pipelines and cables in the coastal zone, whenever such installations
shall have reached the end of their life cycle and are no longer
required. In planning for the termination and abandonment or removal
of pipelines/cables in the coastal zone, the environmental and socio-economic
problems associated with the different options should be carefully
examined.
|
10.1 For the safety of the public and wildlife, all equipment and
above-ground facilities should be dismantled and removed, and the
surface area of the land appropriately restored. Wherever circumstances
allow, consideration should be given to alternative uses of sites
and structures.
|
10.2 It is likely that the process for removal of buried or submerged
pipelines/cables would probably generate negative environmental
impacts of similar extent to those delivered during the installation
process. The cost of miti-gating such impacts and of restoring the
routes after removing the pipelines/cables must be assessed.
|
10.3 To avoid the cost and environmental impact of removing unwanted
pipelines/cables from the coastal zone, it is often acceptable to
leave them in place. If they are left in place they must be disconnected
from any facility, and pipelines must be purged with freshwater,
air or inert gas, and capped at open ends.
|
|
|